Bathroom Remodel Schedule
Week 1
Monday: Demo
Mask off work area and put down Ram Board to protect flooring for the duration of the project.
Set up Hepa air filtration
Demo Existing bathroom and haul away materials
Tuesday: Electrical
Electrician will come and update/install in the morning
Any framing repairs or updates will be made after the electrician is done
Wednesday: Plumbing
Plumbers will come to update/install in the morning
Wallboard and drywall installation will start after plumbers are done
Thursday: Prep
Prep work for tile will begin. Waterproofing, underlayment, etc
Drywall repairs tape/mud
Friday: Prep
Finish up any prep work and begin planning layout for tile
Get tile tools and material set up
Drywall repairs tape/mud
Week 2
Monday,Tuesday,Wednesday
Tile and coverings installation will start
Typically takes 3-4 days for tile
Grout, silicone, seal
Thursday
Finish and cleanup any tile work
Install vanity, toilet, etc
Prep for paint
Friday
Paint
Install grab bars, towel bars, etc
Install any baseboard/trim
Finish and give customer walk through